Advanced Packaging Expansion: 2.5D/3D and HBM Capacity Ahead
As advanced process nodes approach physical limits, there is less room to lift compute through front-end fabrication alone, and the performance gap is increasingly closed at the packaging stage. Driven by the bandwidth and heterogeneous integration needs of AI compute chips, advanced packaging has moved from a back-end assembly step to a critical position in the supply chain. Chinese OSAT leaders and newcomers have repeatedly raised capital expenditure, concentrating funds on 2.5D/3D, wafer-level packaging and memory-related test. Yet packaging capacity takes a long time to build and equipment lead times are slow, so near-term shortages cannot be closed instantly even with heavy spending.
Where this round of expansion is aimed
Based on disclosed projects, most new capacity concentrates on advanced packaging routes. The first is 2.5D/3DIC three-dimensional integration, stacking multiple dies horizontally and vertically on a substrate or silicon interposer to break the single-reticle size limit for high-performance compute and AI accelerators. The second is wafer-level packaging (WLP) together with redistribution and bumping platforms. The third is system-level test for high-density, high-capacity memory chips, paired with high-bandwidth memory such as HBM. The fourth is high-end power module packaging, such as FCLGA-type packages and modules, serving the high-power supply needs of AI servers. Expansion of mature wire-bond packaging stays relatively restrained, with resources clearly tilted toward higher value-added segments.
| Direction | Problem solved | Typical pairing |
|---|---|---|
| 2.5D / 3DIC integration | Heterogeneous die stacking for bandwidth and density | AI accelerators, high-performance compute processors |
| Wafer-level packaging | Smaller form factor, redistributed I/O layout | Portable and high-density integrated devices |
| Memory system-level test | Integrated test for high-bandwidth memory and controller | HBM and large-capacity memory modules |
| Power module packaging | Packaging and modular delivery of high-power devices | AI server power and power modules |
OSATs are raising investment plans in a dense wave
Expansion at leading domestic OSATs has clearly accelerated. JCET raised its 2026 investment plan from RMB 11.01 billion to RMB 18.2 billion, with fixed-asset investment adjusted upward mainly for advanced packaging lines. It plans a high-end advanced packaging factory in Shanghai Lingang in two phases, with total investment of about RMB 7.8 billion; the first phase is scheduled to complete in the second half of 2028. A proposed private placement would fund high-performance compute packaging, high-end power module packaging, wafer-level process upgrades and system-level test for memory chips. Tongfu Microelectronics centers its expansion on high-end AI packaging for a core customer, with a markedly higher planned 2026 investment, and fundraising covering memory, automotive electronics, wafer-level and high-performance compute packaging. SJ Semiconductor started two RMB-ten-billion-scale projects aimed at 3DIC volume production; overseas, ASE Group has also committed funds to expand high-end packaging. At industry events, an executive of a packaging firm judged the global high-end packaging market to grow sharply year on year in 2026, noting China's OSAT capacity ranks among the world's largest, with several mainland firms in the global top ten outsourced packagers.
Capacity cannot be released on demand
The difficulty in advanced packaging expansion is not capital but cycle time and supporting supply. A new packaging plant generally takes two to three years to reach production; key equipment lead times are long, with some high-end packaging tools taking more than six months to deliver. After a line is built, process tuning, yield ramp and customer qualification are still required before orders can be stably accepted. This means even with many projects announced today, effective capacity released over the next one or two years remains limited, and tightness in high-demand segments will likely persist for a while. Upstream equipment, materials and process capabilities in turn constrain how fast expansion lands.
Read-through for procurement and solution teams
For projects involving compute, memory and high-power devices, packaging should enter early supply-chain evaluation rather than being sourced after the chip is finalized. For concentrated advanced packaging types, confirm production slots and capacity reservation with the packaging partner early, and keep longer lead times for critical projects. Retaining some compatibility in package form and substrate design during solution development leaves an alternate path if capacity tightens. When tracking expansion, it matters more to watch equipment arrival, yield ramp and customer qualification— the nodes that truly determine capacity release—than to follow headline investment amounts alone.
Overall, advanced packaging has become one of the main paths to raise system performance in the post-Moore era, and this buildout wave is a medium-term response to AI compute demand. Capacity release, however, is bounded by equipment, construction and qualification cadence, leaving structural tightness in the near term. For the supply chain, forward planning and reserved flexibility are safer than scrambling for capacity once a gap appears. This article is an industry information review and does not constitute investment advice.